Project

Lotos PB

zdjęcia na wymianę lotos (1)

As a company specializing in HVAC systems, we undertook the implementation and installation of ventilation systems for the offshore sector.

The work included the prefabrication and installation of ventilation ducts of the combined weight of 26 tons. The project presented high-quality requirements as each welding joint was subject to NDT inspections and assembly under QC.

The modernization work for the EFRA project began in 2017 and focused on three petroleum distillation plants. The scope included the installation of pipelines from 0.75 to 6 inches in the existing plant. Considering the work area both, assembly and welding tasks required the highest quality.